| |
|

Court Must Raise Statute of Limitations Despite Government Waiver
Although the government waived its challenge to the
timeliness of an action in the Court of Federal Claims, the Court of Appeals for
the Federal Circuit properly raised the issue on its own, because the absolute,
jurisdictional, nature of the statute of limitations prevented an equitable
tolling of the limitations period and could not be waived by the parties,
according to the United States Supreme Court. The contractor brought suit in the
CFC, alleging various government activities on leased land amounted to an
unconstitutional taking of its leasehold rights. The government initially
challenged the claims as untimely under the CFC's six-year statute of
limitations (28 USC 2501), but subsequently conceded the issue and won on the
merits. The contractor appealed the adverse judgment to the Federal Circuit,
which addressed the statute of limitations issue sua sponte, finding the
action untimely. Generally, the law treats limitations as an affirmative defense
the defendant must raise at the pleading stage, and this defense is subject to
the rules of waiver. Besides protecting a defendant's case-specific interest in
avoiding stale claims, some statutes of limitations seek to achieve a broader
system-related goal, such as limiting the scope of a governmental waiver of
sovereign immunity. In precedential opinions going back to 1883, the Supreme
Court had read the time limits of these statutes as more absolute, requiring a
court to decide the timeliness question despite a waiver. In these situations,
the statute's limitations period is "jurisdictional" and not
susceptible to equitable tolling.
Stare Decisis
Given the precedent, the contractor could succeed
only by convincing the Court to overturn prior rulings, which the contractor
failed to do. Although the Supreme Court previously applied equitable tolling to
a limitations statute governing employment discrimination claims (Irwin v.
Dept. of Veterans Affairs, 498 US 89 (1990)), the limitations period in that
case differed from the CFC statute at issue here because the Court had not
previously provided a definitive interpretation. In addition, the Irwin
court did not overturn prior rulings on the jurisdictional nature of the CFC's
statute of limitations. Rather, Irwin recognized a general prospective
rule, but it did not imply revisiting past precedents. Despite the contractor's
reliance on recent cases that interpreted statutes of limitations in actions
against the government as treating the government like other litigants, basic
principles of stare decisis required the Court to reject this line of
reasoning as the earlier cases did not produce "unworkable" law.
According to the Court, a "reexamination of well-settled precedent could
nevertheless prove harmful," and a decision overturning a settled matter
because it was no longer "right" would "threaten to substitute
disruption, confusion, and uncertainty for necessary legal stability."
Dissent
In dissent, Justice Stevens challenged the majority
opinion's reliance on stare decisis, arguing the older cases cited by the
Court were "no longer good law," and if there is any ambiguity in
those cases, the Court should have resolved the matter in favor of clarifying
the law, "rather than preserving an anachronism whose doctrinal
underpinnings were discarded years ago." Justice Ginsburg also dissented,
contending the majority's decision not to reconcile older rulings with more
recent opinions damages "the coherence of the law" by adhering to
"outworn precedent" at odds with "more enlightened
decisions." According to her, it would have been appropriate to overrule
precedent that had become a "positive detriment to coherence and
consistency in the law." (John R. Sand & Gravel Co. v. U.S., US
SCt, 52
CCF ¶78,875)
(The news featured above is a selection from the news covered in the Government Contracts Report Letter, which is published weekly and distributed to subscribers of the Government Contracts Reporter. )
|
|
|
|