| |
|

Severin Doctrine Barred Subcontractor's Delay Claim
A prime contractor's claim on behalf of its
subcontractor for excess costs allegedly incurred as a result of government
delays was summarily denied by the Court of Federal Claims because the
contractor failed to establish it was potentially liable to the subcontractor,
and therefore the claim was barred by the Severin doctrine. The dispute
arose from a contract that called for demolition and removal of military housing
units. According to the prime contractor, its subcontractor's progress was
delayed by work performed by other contractors under the government's control
who allegedly "took more time than called for to remove ... contaminated
soils" at the work site. The government moved for summary judgment, arguing
the contractor's delay claims were barred by the Severin doctrine
because, under the subcontract's "no damage for delay" clause, the
contractor had no potential liability to the subcontractor for project delays.
Therefore, according to the government, the prime could not "pass
through" the subcontractor's delay claims. The contractor countered that,
under applicable state law, the "no damage for delay" clause did not,
as a matter of law, completely immunize the prime from potential liability to
its subcontractor.
Evidentiary Burden
Under the Severin doctrine, the government
bears the burden "to prove that the prime contractor is not responsible for
the costs incurred by the subcontractor that are at issue in the pass-through
suit." For purposes of summary judgment, if the government meets this
burden, then the contractor must present evidence of its potential liability to
the subcontractor. Here, the government met its Severin evidentiary
burden by relying on the unambiguous "no damage for delay" clause in
the subcontract, which was enforceable as a matter of law and provided an
"iron-bound" bar against liability for delay-related claims under
state law. A state law exception that would exempt the clause from enforcement
did not apply to subcontracts between private parties under a contract involving
the federal government. Moreover, a state supreme court ruling on the
enforceability of "no damage for delay" clauses in construction
contracts between two parties held "[t]he parties had a right to agree upon
the exclusive remedy available to the contractors by reason of... delay."
Accordingly, the subcontract immunized the prime from any potential liability to
its subcontractor for delay-related damages. (Harper/Nielsen Dillingham
Builders, Inc. v. U.S., FedCl, 52
CCF ¶78,934)
(The news featured above is a selection from the news covered in the Government Contracts Report Letter, which is published weekly and distributed to subscribers of the Government Contracts Reporter. )
|
|
|
|