| |
|

Summary Judgment Denied on Accounting Practice Change
The government's summary judgment motion on a claim
by a ship repair contractor for unrecovered dry dock certification costs was
denied by the Armed Services Board of Contract Appeals because the record was
insufficient to determine whether an accounting change sought by the contractor
was justified. The contractor appealed a contracting officer's denial of its
claim under a cost-reimbursement contract for advance planning to perform
repairs and alterations to auxiliary oiler explosive class ships. The base
contract included government options for dry dock work, and the contractor was
required to maintain a dry dock in certified status and have it ready and
available for both scheduled and unscheduled repairs should the government
exercise its options. The contractor incurred costs to achieve and maintain
government certification of the dry dock, and it sought to account for the
certification expenses as direct costs to the base contract, which was a change
from its prior practice of allocating these type of costs as indirect.
Cost Principles
In its motion, the government argued the
contractor's claim under the base contract failed because the genesis of the
claim was the government's decision not to exercise dry dock options on a number
of ships, which was fully within its discretion. According to the government,
the contractor had previously charged its dry dock costs as indirect, but now
sought an inconsistent and retroactive change after contract award. The
contractor countered that the appeal concerned not the government's failure to
exercise the options but rather the government's promise under the base contract
to reimburse the contractor for its costs of maintaining the dry dock in a state
of readiness. The contractor contended it had sought the accounting change at
issue from the government before entering into the base contract and that
pending the establishment of an equitable method to charge the certifications
costs as they were incurred, it "provisionally" allocated them as
indirect costs based on dry dock usage, which was its standard accounting
practice under prior contracts. Although the base contract did not mention
recovery of dry dock certification costs as direct costs, the contract's
Allowable Cost and Payment clause incorporated the cost principles of Subpart
31.2 of the Federal Acquisition Regulation, which generally require a
consistent accounting for direct costs as they relate to a particular final cost
objective or an appropriate allocation of costs to an indirect cost pool when
there are two or more cost objectives. Given these considerations, the record
required development to determine whether the accounting change sought by the
contractor was warranted, prospective, allowable, and unreasonably denied, as it
asserted, or was unjustified and impermissibly inconsistent and retroactive, as
the government argued. (Todd Pacific Shipyards Corp., ASBCA, ¶92,325)
(The news featured above is a selection from the news covered in the Government Contracts Report Letter, which is published weekly and distributed to subscribers of the Government Contracts Reporter. )
|
|
|
|