September 2009


From the editors of Wolters Kluwer Law & Business, this update describes important developments from CCH energy publications.

If you have any comments or suggestions concerning the information provided or the format used, we'd like to hear from you. Please send your comments to pamela.maloney@wolterskluwer



Electric Utilities

New Bonneville ASC Methodology Approved
The Commission has approved the revised methodology for determining the average system cost (ASC) used by Bonneville Power Administration in its Residential Exchange Program. Bonneville's revised ASC methodology comprises the following three main components: (1) Provisions related to the calculation of the Base Period average system cost ; (2) provisions relating to the escalation (or change) of the Base Period average system cost to the Exchange Period average system cost; and (3) provisions relating to Bonneville's average system review process and procedures. Bonneville explained that the revised ASC methodology retained characteristics of the previous ASC methodology. The key differences were how average system costs are calculated as well as the substance of the costs included and excluded from the average system costs calculation. Bonneville stated that the revised ASC methodology adopted a streamlined approach to the average system cost calculations by using a different source of average system cost data, i.e., FERC Form 1 data, instead of state retail rate orders. (CCH FERC Statutes and Regulations Edition, ¶31,295)

ISO-NE Market Manipulation Allegations Set for Hearing
Two complaints, one filed by the Attorney General for the State of Connecticut (Connecticut Attorney General) and jointly by the Connecticut Department of Public Utility Control (CT DPUC) and the Connecticut Office of Consumer Counsel (CT OCC) relating to the bidding activity of some market participants importing capacity over the Northern New York AC interface, were set for hearing by the Commission. Under the market rules in ISO New England (ISO-NE), participants with installed capacity (ICAP) import contracts must submit a supply offer or self-schedule for the energy equivalent of the import contract amount for each operating day. The Connecticut parties alleged that between January 2005 and January 2009, every market participant that had submitted a supply offer above $660/MWh over the Northern New York AC Interface failed to perform every time it was dispatched, for a total of 108 such instances, and they alleged that these market participants had been paid a collective $85.5 million in capacity payments. In their amended complaint the Connecticut Parties continued to seek a hearing and investigation into the allegedly fraudulent, manipulative scheme conducted over the two-year period and for which the parties were paid at least $50.9 million for reliability services that their conduct demonstrated they never intended to provide. The Commission noted that the disputed issue in the complaints was the capacity importers’ intent behind the high-priced offers. However, because of the unique history of the allegations, including the ISO-NE’s inconsistency regarding the allegations, the Commission set the issues related to the allegations regarding the capacity importers’ bidding strategy and the market manipulation allegations for hearing. (Richard Blumenthal, Attorney General for The State of Connecticut v. ISO New England Inc., et al., 128 FERC ¶61,182 (ip access users))

FERC Transmission Pricing for PJM Interconnection Upheld in Part
The transmission of energy in the PJM Interconnection using a Ohio utility’s facilities will be priced at the marginal cost of transmitting the energy and will not reflect sunk costs, the U.S. Court of Appeals for the Seventh Circuit ruled. The American Electric Company’s facilities were built before PJM became a Regional Transmission Organization in 2001, and because the facilities were intended to service American Electric’s customers only, there was no economic basis for shifting any part of their costs to other PJM members. Judge Posner characterized the utility’s request as an attempt to stand between western sellers of electricity and eastern buyers and extract a toll that had no relation to the costs of actually providing the transmission service. However, the court rejected FERC’s decision to approve the financing of high-voltage transmission lines in PJM’s system using a pro rata basis to the participating utilities, rather than the previously-used method of allocating the costs according to the expected benefit each utility would receive. (ICC v. FERC, 7thCir 2009, CCH Utilities Law Reporter ¶14,752).

BP Energy To Pay $4.7 Million to NV Energy
The Commission approved an uncontested settlement between NV Energy, Inc. (NV Energy), formerly Nevada Power Company, the Office of the Nevada Attorney General, Bureau of Consumer Protection, and BP Energy Company (BP). After the Western energy crisis of 2001, NV Energy filed a complaint with the Commission to modify contracts signed during the crisis. The joint offer of settlement and settlement agreement were fair and reasonable and in the public interest, according to the Commission. BP agreed to make a one-time, lump-sum $4.7 million payment to NV Energy in return for NV Energy’s and the Nevada Bureau of Consumer Protection’s release of all claims against BP. The settlement was a full and final settlement of the issues in the proceedings relating to BP’s forward sales contracts executed with NV Energy’s predecessor, Nevada Power Company, between March 12, 2001 and June 20, 2001, at market-based rates. (Nevada Power Co. v. BP Energy Co., 128 FERC ¶61,185 (ip access users))

Natural Gas

Comments Sought on Quarterly Reporting Proposal
The Commission is seeking public comment on the proposed standardized electronic information collection to be used by Natural Gas Policy Act (NGPA) and Hinshaw pipelines for submitting the quarterly transactional reports as detailed in a recent proposed rulemaking (See FERC Statutes and Regulations, ¶32,644. This notice also extends the deadline for comments on the proposal from October 27 to November 2, so that all comments will be due on the same date. Under the proposal's provisions, these quarterly reports would have to contain, for each transportation and storage service provided during the preceding calendar quarter, information including: (1) The type of service performed (i.e., firm or interruptible transportation, storage, or other service); (2) the rate charged under each contract, specifying the rate schedule/name of service and docket where the rates were approved--the report also should separately state each rate component set forth in the contract (i.e. reservation, usage, and any other charges); and (3) and the primary receipt and delivery points covered by the contract, including the industry common code for each point. (FERC Statutes and Regulations Edition, ¶35,051)

Hedge Fund Settles Charges for $7.5 Million
The Commission approved the uncontested joint settlement entered into by Amaranth Advisors LLC (Amaranth), its subsidiaries, and the Commission’s Enforcement Litigation Staff in order to settle all claims against Amaranth that arose out of conduct alleged to have been in violation of the Commission’s trading regulations. The settlement agreement also resolves claims brought by the Commodity Futures Trading Commission. In the joint settlement, Amaranth did not admit or deny the allegations set forth in the show cause order, but it did stipulate to a number of facts concerning its trading activities. Specifically, Amaranth admitted that the NG Futures Contract settlement prices on February 24, March 29, and April 26, 2006, would have been different if Amaranth had not traded during the settlement periods on those days, and that the value of its swap positions would have been lower if the NG Futures Contract settlement prices had been higher than it actually was. Amaranth was obligated by the settlement agreement to pay $7.5 million to the U.S. Treasury. The parties agreed that the order approving the settlement agreement was final and non-appealable, and Amaranth waived its right to rehearing and judicial review. (Amaranth Advisors LLC, et al., 128 FERC ¶61,154 (ip access users))

Oregon’s Challenge to Bradwood Denied
The State of Oregon’s requested rehearing of a Commission order [126 FERC ¶61,035 (ip access users)] denying another rehearing request of the Commission’s grant of authority to Bradwood Landing LLC (Bradwood) and NorthernStar Energy LLC (NorthernStar) to site, construct, and operate a liquefied natural gas (LNG) import terminal on the Columbia River at Bradwood, Oregon and the accompanying pipeline, was denied by the Commission. Oregon alleged that, without a stay, it would have to expend additional time and money reviewing NorthernStar’s mitigation plans and final designs and attending meetings. The Commission found that Oregon did not meet its burden to demonstrate that it would suffer irreparable harm absent the granting of the stay. Oregon also argued that the Commission failed to comply with the Endangered Species Act by not initiating formal consultation with the National Marine Fisheries Service and the U.S. Fish and Wildlife Service. The Commission noted that its order [126 FERC ¶61,035 (ip access users)] fully addressed this argument and that it was fully complying with the ESA. Finally, Confederated Tribes of the Umatilla Indian Reservation’s (CTUIR) motion to intervene out-of-time was denied again. CTUIR’s motion was filed more than two years after the deadline for filing of timely interventions. Therefore, CTUIR would have to meet a higher burden necessary to grant the late motion, and the Commission found that it failed to do so. (Bradwood Landing LLC, et al., 128 FERC ¶61,216 (ip access users))

Oil

Mobil Not Granted Authorization To Charge Market-Based Rates
In an initial decision, an administrative law judge (ALJ) determined Mobil Pipeline Company (MPLCO) should not be granted authorization to charge market-based rates on its existing Pegasus pipeline system (Pegasus) for the transportation of crude oil. The ALJ also determined the appropriate origin market, whether MPLCO lacked significant market power, and whether authorization to charge market-based rates would result in rates that were just and reasonable. The Pegasus is an 858-mile, 20” diameter pipeline that transports crude oil from its origin at Patoka, Illinois to Nederland, Texas. The ALJ found that MPLCO had not established that currently there were no good economic alternatives to Pegasus’ services in its’ origin market that would hold Pegasus’ rates to reasonable levels. The ALJ concluded that MPLCO had not shown that the origin market was sufficiently or workably competitive such that an authorization by the Commission to charge market based rates for its oil transportation services would result in rates that were just and reasonable. Therefore, the ALJ recommended that MPLCO’s application for market-based rate authority be denied. The potential for market abuse exists through the exercise of market power possessed by MPLCO, as the evolution towards a competitive market in which there was adequate pipeline capacity between the Upper Midwest and the Gulf Coast was not yet complete; the structure of Pegasus’ defined origin market was ill-equipped for workable competition; and the supply/demand imbalance had caused market disequilibrium. (Mobil Pipe Line Co., 128 FERC ¶63,008 (ip access users)).

Hydro

Hydro Project Relicensing Order Vacated
The U.S. Court of Appeals for the Second Circuit found that an action by the Federal Energy Regulatory Commission (FERC) denying a municipal power authority’s request to intervene during proceedings involving the relicensing of the School Street Project Dam, located on the Mohawk River in New York, was not only arbitrary and capricious, but may have constituted prejudicial error. Because the court could not conclude that the outcome would have not been different if Green Island Power Authority had been allowed to intervene, it vacated the FERC order issuing the new license in 2007 and remanded the case for further proceedings. However, the Adirondack Hydro Development Corporation, which also sought to intervene in the action, lacked standing to challenge any of the FERC orders. The Second Circuit found that Adirondack offered no argument that its own hydroelectric project would be impacted by the relicensing of the School Stream Project, and its purported interest in developing future projects on the Mohawk River was too hypothetical. (Green Island Power Authority v. FERC, 2ndCir 2009, CCH Utilities Law Reporter 14,753).

Nuclear Power

Breach of Contract Award Must Be Based on 1987 ACS
Two utilities' damages award of $82,789,289, resulting from a judgment against the Department of Energy (DOE) for its partial breach of contract to accept spent nuclear fuel (SNF) from the utilities in a timely manner, had to be recalculated because the trial court based the award on a model expressly rejected by the U.S. Court of Appeals for the Federal Circuit. While the utilities incurred substantial mitigation costs in storing SNF that otherwise would have been stored by DOE under the contract, the trial court improperly based the calculation of the award on the utilities' argument that DOE would have accepted 3000 metric tons of uranium from them if it had not breached the contract. This volume was based on a model developed by the utilities hypothesizing that DOE would begin accepting the SNF on schedule in 1998. In reality, however, the award needs to be recalculated on a more realistic basis--the June 1987 acceptance capacity schedule (ACS) process, which provides the best available pre-breach indicator of both parties' estimates of the time-frame in which the SNF would be accepted. (Carolina Power & Light Co., et al. v. U.S. (FedCir) CCH Nuclear Regulation Reporter, ¶20,690)

Claims of Radiation Injury Failed Due to Lack of Causation
Claims of radiation injuries to residents of a Colorado town which had been the site of a uranium and vanadium milling facility failed for lack of evidence of factual causation and their medical monitoring claims failed for lack of evidence of bodily injury as required by the Price-Anderson Act, which governs claims arising from nuclear incidents. Affirming a district court decision, the 10th Circuit Court of Appeals found that cancer and thyroid disease, the illnesses reported by the residents, can have multiple causes. The residents did not show that the milling operation was a substantial factor that contributed to their illnesses, as required by tort law. Finally, under the Price-Anderson Act, the asymptomatic DNA damage and cell death suffered by some of the residents as a result of exposure to radiation did not constitute, per se, bodily injury. (Gary June, et al. v. Union Carbide Co., et al. (10thCir) CCH Nuclear Regulation Reporter ¶20,691)

Mineral Management Service

Protection of Reprocessed Geophysical Information Extended
Minerals Management Service (MMS) finalized a rule extending the proprietary term of certain reprocessed geophysical information submitted to MMS under permits. The rule gives up to 5 years of additional protection to reprocessed vintage geophysical information that MMS retains and, without extensions, is subject to release by MMS 25 years after a permit is issued. MMS believed the extension will provide incentives to permittees and third parties to reprocess, market, or in other ways use geophysical information that might not otherwise be reprocessed without the term extension. The extension does not apply to geological data or information. The rule became effective on September 14, 2009. (CCH Energy Management, Issue No. 1303, ¶9453).