October 2006

From the editors of CCH's government contracts products, here are summaries of the important recent developments in this practice area for the past month.  Complete coverage of these issues, and many more, appear in the Government Contracts Reporter and related products.

If you have comments or suggestions concerning the information provided or the format used, please feel free to contact me directly at aaron.broaddus@wolterskluwer.com.

Legal News


Failure to Prove Reliance on Defective Data Barred Price Reduction
A board of contract appeals' denial of a claim for a contract price reduction was affirmed by the Court of Appeals for the Federal Circuit because the government did not establish it detrimentally relied on defective cost or pricing data. The government sought a $300 million price reduction on a six-year contract to manufacture military aircraft engines, alleging the contractor provided defective cost or pricing data. The Truth in Negotiations Act requires a price adjustment if inaccurate, incomplete, or noncurrent cost or pricing data increased the contract price. On reconsideration, the Armed Services Board of Contract Appeals found the base-year contract price was based on the contractor's best and final offer, but the government did not review the BAFO cost or pricing data prior to award and relied on "competitive forces" for subsequent awards and options. All of the government's TINA claims were denied because it failed to establish reliance on the allegedly defective BAFO cost or pricing data and thus failed to show defective data caused an increase in the contract price (05-1 BCA ¶32,860).

On appeal, the government argued its entitlement to a price adjustment hinged on showing the contract price was based on defective data, not that it actually relied on the data to its detriment. The court agreed the government was entitled to a presumption any defective cost or pricing data affected its agreement to the contract price and thus actually caused a price increase. However, precedent held this presumption was rebuttable, not conclusive. Once the contractor rebutted the presumption of causation, the government was required to establish detrimental reliance on the defective data (33 CCF ¶74,555). Moreover, the reliance requirement was consistent with Congressional intent, as demonstrated by the subsequent codification of the requirement as a defense to a TINA claim (10 USC 2306a(e)(2)). (Wynne, Sec'y of the Air Force v. United Technologies Corp., CA-FC, 50 CCF ¶78,603; Government Contracts Report Letter No. 1878, October 4, 2006)


30-Day Delay in Terminating for Default Did Not Constitute Waiver
The government did not waive its right to terminate a contract for default, according to the Armed Services Board of Contract Appeals, because it terminated within a reasonable time after the default and did not encourage continued performance. The dispute arose from a contract for an anti-aircraft missile defense system, which the contractor planned to obtain from a foreign government. Numerous delivery issues arose after contract execution, and after seven time extensions, the government terminated the contract for default based on the failure to deliver the system. On appeal, the contractor sought to convert the default termination into a termination for convenience, arguing the government waived its right to terminate for default.

The board explained that to establish a waiver of the right to terminate for default, a contractor must show: "(1) [t]he government failed to terminate within a reasonable time after the default under circumstances indicating forbearance; and (2) [the contractor] relied upon the failure to terminate and continued performance with the government's knowledge and implied or express consent." Here, the contracting officer issued a show cause notice on the amended delivery date and gave the contractor 16 days to reply. The CO told the contractor 12 days later he was considering a termination and requested justifications for the nonperformance. On the 15th day following non-delivery, the contractor suggested a meeting with the foreign government supplier and the CO responded the contract was going to be terminated. Four days later, when the contractor advised the supplier was ready to deliver, it was told to take no further actions on behalf of the government. The contract was terminated four days later, on the 30th day following non-delivery. The short delay in terminating was not unreasonable under the circumstances, and none of the government's communications could be interpreted as encouraging performance after the delivery date. There was also no evidence the contractor justifiably relied on the government's failure to terminate immediately or continued performance with the government's knowledge and implied or express consent. (Range Technology Corp., ASBCA, 06-2 BCA ¶33,371; Government Contracts Report Letter No. 1875, September 13, 2006)


Government Ordered to Compensate For Terminated Permit
The government was ordered to compensate the owner of a lodge operated under a term special use permit because it closed road access to the property, effectively terminating the permit and giving rise to relief. The lodge owner sought to recover damages stemming from the government's decision to close two deteriorating bridges linking the only access road to the lodge and not to fund replacements. The special use permit governing the property restricted activity on the site to the operation of a "public lodge." Therefore, the bridge closures effectively closed the lodge, as the property could only be viably operated if the public had vehicular access to the lodge. The permit provided for relief to the lodge owner if the government terminated the permit in the public interest by obligating the government to pay "equitable consideration for the improvements." Although the government did not terminate the permit by issuing a formal document, the actions it took to eliminate access to the lodge effectively terminated the permit and entitled the lodge owner to compensation.

The government challenged the owner's right to compensation, arguing that before the bridge closings the owner did not operate the site as a public resort and failed to notify the government about the potential sale of the limited liability company operating the facility. However, during the period of inactivity the government did not require the lodge to operate due to a major road construction project in the area. Moreover, the government never provided the requisite notice of a proposed revocation of the permit. Also, the permit required notice to the government if the owner contemplated a sale of its interest in the permit, but did not require notice of the sale of the ownership interest in the company operating the lodge. Accordingly, the government was ordered to compensate the lodge owner for the value of the improvements located on the permit site, as well as post-termination expenditures. Because the permit did not directly benefit the government, the lodge owner was denied Contract Disputes Act interest on the award. (The Sweetwater, A Wilderness Lodge LLC v. U.S., FedCl, 50 CCF ¶78,601; Government Contracts Report Letter No. 1877, September 27, 2006)


Contractor Was Entitled to Costs Incurred Outside Scope of Orders
According to the Department of Transportation Board of Contract Appeals, the government was estopped from denying costs for services performed outside the period specified by task orders because the government knew of the overrun, induced continued performance and represented it would fund the performance, and the contractor relied on the government's conduct to its detriment. The dispute arose out of an indefinite quantity/indefinite delivery contract for technical support services where performance was to be based on the issuance of term and completion task orders. The contract stated "[t]he contractor shall not perform work hereunder nor incur any costs hereunder until it receives a specific task order signed by the contracting officer." The contract also provided "[c]osts incurred prior to the beginning date or after the ending date [of a task order] shall not be directly allowable without the written consent of the [CO]." A Limitation on Funds clause required the contractor to notify the government in the event it believed its costs would exceed 75 percent of the total amount of funds allocated to any particular task order. On several occasions the contractor incurred costs and performed work prior to the commencement or after the expiration of a task order. Despite directing the contractor's attention to the contract provisions and advising it that costs incurred without authorized task orders may be disallowed, the government established a pattern of retroactively extending performance periods and funding the work. The government later denied costs incurred under similar circumstances, stating performance had not been authorized because no task order had been in effect during the disputed period and notification of the overruns had not been provided.

In general, "the government is not obligated to reimburse a contractor for any amount beyond the funds allotted to the contract," and retroactive funding of overruns "neither waive[s] the notification requirements for subsequent overruns nor bind[s] the government to fund later overruns." However, the government may be obligated to fund an overrun if it has knowledge of the overrun and promotes continued performance by representing additional funding will be provided. Here, the record showed the government knew at all relevant times the contractor was performing work during the periods in dispute. In addition to the government's pattern of retroactively authorizing task orders, the urgency of the work gave the contractor reason to believe it would be compensated despite the absence of written authorization. As most of the task orders contained clauses stating the services were "critical" work requiring "daily technical support," it was unlikely the government desired the contractor to cease performance during the disputed periods. The contractor therefore justifiably relied on the government's conduct in continuing performance and was entitled to reimbursement of its incurred costs. (Base Technologies, Inc. v. U.S. Dept. of Transportation, DOT BCA, 06-2 BCA ¶33,380; Government Contracts Report Letter No. 1877, September 27, 2006)

Legislative and Regulatory Activity


Congress Approves FY 2007 DoD Appropriations Bill

The House and Senate approved a conference report to HR 5631, legislation funding the Department of Defense in fiscal year 2007. The House passed the report by a 394-22 vote on September 26 while the Senate approved it 100-0 on September 29. The conference report reconciled competing FY 2007 DoD budgets passed by each chamber. The House version, which passed on June 20, allocated $427.6 billion, including $81.8 billion for procurement. The Senate voted September 7 for a $469.7 billion budget with $81 billion for procurement. In its final version, the bill will allocate $447.6 billion for the DoD's FY 2007 budget, including $80.9 billion for procurement. [President Bush signed the bill into law on September 29.] (Government Contracts Report Letter No. 1878, October 4, 2006)


New Website Will Inform Public About Federal Grants, Contracts
President George W. Bush signed the Federal Funding Accountability and Transparency Act (S. 2590) on September 26. The bipartisan legislation, calls on the Office of Management and Budget to establish a new website that will provide information about government grants and contracts greater than $25,000, except those that must remain classified for national security reasons. The legislation requires OMB by January 1, 2008, to establish a single, searchable website where citizens will be able to access information for each federal grant or contract within 30 days of its award, including: (1) the name and location of the corporation, association, state or locality or other entity receiving the award; (2) the name of the agency funding the award; (3) the amount of the award; and (4) the purpose of the award. The website is in addition to "ExpectMore.gov," established earlier this year to allow the public to see how well Federal programs are performing, and "Results.gov," established in 2002 to provide information on the President's agenda for improving federal agency management. (Government Contracts Report Letter No. 1878, October 4, 2006)


House Passes Bill Making Prison Industries Compete

The House of Representatives on September 14 approved the Federal Prison Industries Competition in Contracting Bill of 2006 (HR 2965), a bill allowing more private competition for contracts performed by Federal Prison Industries (FPI). The Senate must still pass the measure for it to become law. HR 2965 would establish governmentwide procurement policies for FPI based on competition. FPI currently produce goods and services for the federal government, such as electronic products and furniture, on a noncompetitive basis. The bill would phase out noncompetitive contracts by October 1, 2011. Until then, federal agencies would still be required to contract with FPI for goods and services it offered. However, the items cannot exceed a fair and reasonable price, as determined by the Federal Acquisition Regulation. The contracts would also have to meet procurement and time requirements. Contracts for products or services not currently offered by FPI would require FPI's chief operating officer to study and report the impact that offering them would have on the private sector. (Government Contracts Report Letter No. 1876, September 20, 2006)

Major Contract Awards


Lear - $1.9 Billion. Lear Siegler Logistics International Inc., Gaithersburg, MD, is being awarded a $1,900,000,000 indefinite delivery/indefinite quantity with fixed-price contract. This contract supports numerous aircraft and weapons systems including the C-47, T-33, T-37, C-130, F-111, F-4, F-5, F-16, and various commercial aircraft. This is a Foreign Military Sales (FMS) contract that will support numerous FMS countries. These countries purchase nonstandard and hard to support standard supply items, maintenance/repair support, and task orders via this contract. Task orders will be issued to cover more complex maintenance tasks, studies, analysis or technical assistance that will require technicians to travel to the country requiring support. This work will be complete September 2016. Headquarters Air Force Security Assistance Center, Wright-Patterson Air Force Base, OH, is the contracting activity. (Government Contracts Report Letter No. 1875, September 13, 2006)


SAIC - $1.5 Billion. Science Applications International Corp. (SAIC), Fairfield, NJ, is being awarded a maximum of $1,050,000,000 fixed price with economic price adjustment contract for maintenance, repair, and operations (MRO) supplies for Southeast Region, zone 1. Using services are Army, Navy, Air Force, Marine Corps, and federal civilian agencies. This is an indefinite delivery/quantity type contract exercising 2nd option. Date of performance completion is Sept. 17, 2007. Contracting activity is Defense Supply Center Philadelphia (DSCP), Philadelphia, PA. (Government Contracts Report Letter No. 1877, September 27, 2006)


CSC - $628 Million. Computer Sciences Corporation, El Segundo, CA, won a task order to provide technical and business transformation services for the U.S. Air Force Expeditionary Combat Support System (ECSS). CSC estimates the value of the award, which has a 21-month base period with options for an additional 57 months, to be $628 million if all options are exercised. The ECSS contract was awarded under the Enterprise Software Initiative blanket purchase agreement, which CSC originally announced in June 2004, with an estimated value of $250 million. Under the task order, CSC will be the prime systems integrator and provide a full range of services to help the Air Force transform its global supply chain. Services include logistics business process redesign and commercial off-the-shelf enterprise resource planning. (Government Contracts Report Letter No. 1876, September 20, 2006)


Lockheed - $590. Lockheed Martin Corp., Lockheed Martin Mission Systems, Colorado Springs, CO, is being awarded a $589,591,938 firm-fixed-price, indefinite delivery/indefinite quantity, cost-plus-fixed fee, and cost-plus-award fee contract to provide for Air and Space Operations Center Weapon System Integrator to include fielding, sustainment, system engineering, integration, modernization, maintenance, management, and contingency support for Air and Space Operations Center. The Air Force can issue delivery orders totaling up to the maximum amount indicated above, although the actual requirements may be less than the amount above. This work will be complete August 2010. Headquarters Electronic Systems Center, Hanscom Air Force Base, MA, is the contracting activity. (Government Contracts Report Letter No. 1876, September 20, 2006)


Northrop - $500 Million. New York City's Department of Information Technology and Telecommunications has awarded Northrop Grumman Corporation, Los Angeles, CA, a five-year $500 million contract to provide the city's broadband public-safety wireless network, the most comprehensive network of its kind. This effort will enhance the city's existing mobile wireless communications network with high-speed data and video capabilities, and deploy several new, advanced wireless applications to support first responders and transportation personnel. Northrop Grumman's New York City solution uses standards-based mobile broadband wireless technology, known as the Universal Mobile Telecommunications System, provided by IPWireless of San Bruno, CA. (Government Contracts Report Letter No. 1876, September 20, 2006)


Harper Construction, Stronghold Engineering, Solpac, Douglas E. Barnhart, RQ Construction - $500 Million. Harper Construction Company, Inc., San Diego, CA; Stronghold Engineering, Inc., Riverside, CA; Solpac, Inc. dba Soltek Pacific, San Diego, CA; Douglas E. Barnhart, Inc., San Diego, CA; RQ Construction, Inc., Bonsall, CA, are each being awarded a firm-fixed-price, indefinite-delivery/indefinite-quantity multiple award construction contract for new construction, renovation/revitalization/alteration, and repair by design-build or design-bid-build of various bachelor enlisted quarters, bachelor officer quarters (BEQ), and lodges of various roofing systems at various locations within the Naval Facilities Engineering Command (NAVFAC) Southwest area of responsibility (AOR). The total amount per contract is not to exceed $100,000,000 (base period and four option years) with a guaranteed minimum of $25,000, bringing the cumulative total for all five contracts to $500,000,000. Harper Construction Company, Inc. is being awarded the $19,897,265 initial task order for the design and construction of a BEQ at Horno 53 Area at the Marine Corps Base, Camp Pendleton, Oceanside, CA. Work for this task order is expected to be completed by July 2008. The remaining four contractors are being awarded the minimum guarantee of $25,000. The term of the contract is not to exceed 60 months, with an expected completion date of September 2007 (September 2011 with options). These five contractors may compete for task orders under the terms and conditions of the awarded contract. The Naval Facilities Engineering Command Southwest, San Diego, CA, is the contracting activity. (Government Contracts Report Letter No. 1877, September 27, 2006)


United Technologies - $455 Million. United Technologies Corp., Hartford, CT, is being awarded a $455,103,253 firm-fixed-price & cost-plus-fixed fee contract modification. This action provides for F-22/F119 engine (48) Lot 6 production and CY06 field support and training. At this time, $53,610,547 have been obligated. This work will be complete December 2006. Headquarters Aeronautical Systems Center, Wright-Patterson Air Force Base, OH, is the contracting activity. (Government Contracts Report Letter No. 1877, September 27, 2006)


Raytheon - $369 Million.
Raytheon Co., Tucson, AZ, is being awarded a $369,059,572 firm-fixed-price modification under previously awarded contract (N00024-04-C-5460) for Phalanx Close-In Weapons Systems and associated spares for FY06 Navy (51 percent), Army (35 percent), and the Governments of Pakistan (12.8 percent) and Australia (1.2 percent) under the foreign military sales requirements. Phalanx close-in Weapon System (CIWS) is a fast reaction terminal defense against low and high flying, high-speed maneuvering anti-ship missile threats that have penetrated all other ships' defenses. The CIWS is an integral element of the Fleet Defense In-Depth concept and the Ship Self-Defense Program. Operating either autonomously or integrated with a combat system, it is an automatic terminal defense weapon system designed to detect, track, engage, and destroy anti-ship missile threats penetrating other defense envelopes. Phalanx CIWS is currently installed on approximately 187 Navy ships and is in use in 20 foreign navies. Work is expected to be completed December 2009. The Naval Sea Systems Command, Washington, D.C., is the contracting activity. (Government Contracts Report Letter No. 1876, September 20, 2006)

Valero - $289 Million. Valero Marketing and Supply Co., San Antonio, TX, is being awarded a maximum $288,789,146 fixed price with economic price adjustment for jet fuel for Defense Energy Support Center (DESC). Other location of performance is Benicia, CA. This is a 12-month indefinite delivery, indefinite quantity type contract. Date of performance completion is Oct. 30, 2007. Contracting activity is DESC, Fort Belvoir, VA. (Government Contracts Report Letter No. 1875, September 13, 2006)


Boeing - $279 Million. NASA announced that it has extended its Checkout, Assembly and Payload Processing Services (CAPPS) contract with Boeing, Chicago, IL, for three additional years. Valued at $278.5 million, the contract extension and modification covers Oct. 1, 2006, through Sept. 30, 2009. The total contract value including exercised and unexercised options is approximately $846 million. Under the contract, Boeing provides management and technical support of payload processing for the space shuttle, ISS and expendable launch vehicle programs. Services and support include the planning for and receiving of payloads, maintenance of associated ground support systems, integration of payloads with the space shuttle, launch support and space shuttle post-landing payload activities. (Government Contracts Report Letter No. 1877, September 27, 2006)


Shell Oil- $254 Million.
Shell Oil Products U.S., Houston, TX, is being awarded a maximum of $254,184,476 fixed price with economic price adjustment contract for JP8 turbine fuel for DESC. This is a 12 - month, indefinite delivery/quantity type contract. Date of performance completion is October 30, 2007. Contracting activity is DESC, Fort Belvoir, VA.


Tesoro - $253 Million. Tesoro Refining and Marketing Co., San Antonio, TX, is being awarded a maximum of $253,455,069 fixed price with economic price adjustment contract for JP-8 jet fuel for Defense Energy Support Center (DESC). Other location of performance is Kapolei, HI. This is a 12 month, indefinite delivery/ quantity type contract. Date of performance completion is Oct. 30, 2007. Contracting activity is DESC, Fort Belvoir, VA. (Government Contracts Report Letter No. 1877, September 27, 2006)


Donley-Kirlin, FEMCO, Grunley/Goel, Allen & Shariff - $250 Million. Donley-Kirlin JV, Rockville, MD; FEMCO, Inc., Washington, D.C.; Grunley/Goel JV, Landover, MD, and Allen & Shariff/GDI JV, Bladensburg, MD, will be awarded a firm-fixed price, indefinite-quantity multiple award construction contract for stand alone construction and/or design/build projects at various Navy and federal government installations in the Washington metropolitan area. The total contract amount is not to exceed $250,000,000 (base period and four option years). Work is expected to be completed September 2011. The multiple contractors (four in number) may compete for task orders under the terms and conditions of the existing contract. The Naval Facilities Engineering Command Washington, Washington, D.C., is the contracting activity. (Government Contracts Report Letter No. 1876, September 20, 2006)


Petro Star - $152 Million. Petro Star, Inc., Anchorage, AK, is being awarded a maximum of $152,321,965 fixed price with economic price adjustment contract for JP-8 and JP-5 turbine fuel. Using services are Army and Air Force. This is a 12 month, indefinite delivery/ quantity type contract. Other locations of performance are Valdez and North Pole, AK. Date of performance completion is Oct. 30, 2007. Contracting activity is DESC, Fort Belvoir, VA. (Government Contracts Report Letter No. 1877, September 27, 2006)


Northrop - $143 Million. Northrop Grumman Newport News Corp., Newport News, VA, is being awarded a $142,812,292 fixed-price-incentive delivery order modification to previously awarded indefinite-delivery/indefinite-quantity contract (N00024-04-D-4409) for accomplishment of the Depot Modernization Period (DMP) for USS Toledo (SSN 769). The DMP allows necessary maintenance and equipment upgrades to enable SSN 769 to continue to be mission capable. Work is expected to be completed by February 2008. The Supervisor of Shipbuilding, Conversion and Repair, USN, Newport News, VA, is the contracting activity. (Government Contracts Report Letter No. 1876, September 20, 2006)


Phoenix International, Inc. - $125 Million. Phoenix International, Inc., Landover, MD, is being awarded a potential $125,000,000 indefinite-delivery/indefinite-quantity, cost-plus-award fee contract, for engineering and technical services, equipment, material, ships/vessels and/or systems to assist the director of Ocean Engineering, supervisor of Salvage and Diving, in the conduct of worldwide rapid response undersea search, salvage, recovery and rescue operations. The primary purpose of this contract is to provide for the operation and maintenance of Navy-owned undersea search and recovery equipment. Work is expected to be completed by September 2011. The contract was competitively procured and advertised on the Internet, with one proposal received. The Naval Sea Systems Command, Washington, D.C., is the contracting activity. (Government Contracts Report Letter No. 1877, September 27, 2006)


Raytheon - $113 Million
. Raytheon Co., Tucson, AZ, is being awarded a $112,878,214 firm-fixed-price contract modification to provide for 12 AIM-120D AMRAAM Air Vehicles Instrumented (AAVIs), 50 AIM-120D Captive Air Training Missile, 104 AIM-120C7 AMRAAM Air Vehicles, 112 Non-Developmental Item, Airborne Instrumentation Units (NDI-AIUs), proposal preparation, L3 Communications Pulse Code Modulation, Encoder Qualification Non-Recurring Expense, NDI-AIU Test Equipment Upgrade and option for AIM-120 D production transition. Headquarters Medium Range Missile Systems Group, Eglin Air Force Base, FL, is the contracting activity. (Government Contracts Report Letter No. 1876, September 20, 2006)


Northrop - $110 Million. Northrop Grumman, Los Angeles, CA, has been awarded a five-year, $110 million contract to continue its support of the U.S. Army's Battle Command Training Branch (BCTB) program. The award was made by Naval Air Warfare Training Systems Division in Orlando, FL. The company has supported the program since its inception in 2001. The BCTB program provides world-class training and battle simulation services to the Army's III Corps at Fort Hood and Fort Bliss in Texas; Fort Sill in Oklahoma; Fort Carson in Colorado; and Fort Riley in Kansas. Northrop Grumman teammates include General Dynamics, Falls Church, VA; Lockheed Martin, Bethesda, MD; Raytheon, Waltham, MA; Blackhawk Management, Houston, TX; and Huckstep Holding Corporation, Colorado Springs, CO. (Government Contracts Report Letter No. 1876, September 20, 2006)